The Cherry Hill Department of Engineering will continue work on the 2014 Road Maintenance Program next week, with work scheduled to begin Tuesday, June 2, on Doncaster Road and Doncaster Court. All work will be done as weather permits.
Both roads will be resurfaced as part of the project. Planned concrete work includes isolated removal and replacement of sidewalk that is causing trip hazards, as well as removal of driveway aprons and curbs as needed due to grade changes and/or deterioration.
School bus schedules and trash pickup will remain undisturbed; however, parking may be affected during work hours. The contractor will notify affected residents as necessary.
This work is being done as part of the Township's Road Maintenance Program, which consists of the mill and overlay of nearly two dozen roads within the Township and isolated replacement of concrete curbs, sidewalks and driveway aprons.
To learn more about the Road Maintenance Program, contact Bob Lee or Kevin McCormack in the Department of Engineering at (856) 424-3203.